Create Project Plans
Set up project plans.
Create a project.
Security domains in the Project Tracking functional area:
- Manage: Project Plan
- Set Up: Project Details
You can use Workday project plans to capture the details of a project from start to
finish, by:
- Listing the phases and tasks that define your project work.
- Designating milestones for your project.
- Marking specific tasks as nonbillable to exclude the associated work hours from billing and revenue forecasts.
- Marking specific tasks for reports on actual utilization.
- Access 1 of these options:
- Create Project Plantask.
- Project Plannertab on theProject Planprofile group for the project.
Before you can use theProject Plannerreport, you first need to add it to theProject Planprofile group.If you have critical custom validations configured for your tenant, you can't use theProject Planner. - As you complete the project plan, consider:
Option Description Phases and TasksOnce you assign phases and tasks to the project, Workday creates a project-specific instance of them for reporting purposes.If a project plan has more than 500 rows of phases and tasks in the Project Plan grid, Workday has reduced performance.Start DateEnd DateSet these dates to control the number of tasks that workers can select when they enter the time they work on a project.Non-BillableFor billable projects only. You can mark a task as nonbillable to:- Create custom validations to exclude billing for nonbillable tasks.
- Exclude hours from revenue forecast calculations on project budgets.
- Set filters to generate reports listing nonbillable tasks, billable tasks, or both.
MilestoneUse milestones for reporting and invoicing billable projects.UtilizationSelect if the time block for this task qualifies for actual utilization.When selected, you can create a custom report to determine utilization.
Workday populates the project plan with your information.
- Create a multilevel project plan.
- Create a resource plan.
- Allocate workers to project plan tasks.