Setup Considerations: Resource Plans
You can use this topic to help make decisions when planning your configuration and use of
resource plans. It explains:
- Why to set them up.
- How they fit into the rest of Workday.
- Downstream impacts and cross-product interactions.
- Security requirements and business process configurations.
- Questions and limitations to consider before implementation.
Refer to detailed task instructions for full configuration details.
What They Are
Resource plans in Workday help you to staff your projects and enable your workers to
charge their time against a project.
Business Benefits
- Create and update resource plans.
- Reduce data entry for commonly used information.
- Staff your projects with qualified workers.
- Configure custom objects to extend Workday to meet your unique requirements for resource plans.
- Enable project workers to log their time with Workday Time Tracking.
Use Cases
- Specify the window of time that workers can record their hours on a project.
- Control the content of resource plans to reduce effort, maintain consistency, and avoid errors.
- Find qualified workers who are available for project work.
- Balance the distribution of project assignments across your workforce.
Questions to Consider
Questions | Considerations |
|---|---|
Will your resource plans contain common information? | You can create templates for resource plans to populate the common
information that most users need to enter. Templates streamline data
entry and reduce user errors. |
Do you want to enable workers to log their time on any project or
only on assigned projects? | Use the time entry template to enable project workers to log time
to any project, without having an assignment on a resource
plan. Otherwise, you must assign project workers to a resource
plan before they can log time to the project. |
What date range do you want workers to access when they log their
time on a project? | Workers on a resource plan can log time against a project or a
project task. Workday automatically populates the date range with the
start and end dates of the project. You can configure a narrower date
range for workers to log their time on the Edit Tenant
Setup - Financials task by using the dates specified
in:
You can use multiple sources to continue narrowing the
date range. Workers can only log time where the selected date ranges
overlap. |
How will you find workers for your projects? | Workday provides multiple reports that you can use to find workers
to add to your resource plans. You can configure the Find
Workers button to launch the report that best suits
your needs. |
What are the requirements for your project roles? | You can simplify your staffing effort by specifying the
requirements for your project roles. When defined, a Find Worker report
returns the workers who match your requirements. |
Which project roles should you restrict to project
hierarchies? | You can restrict the availability of project roles to specific
primary project hierarchies. This restriction simplifies role selection
and reduces data entry errors. Child hierarchies inherit role
restrictions from their parent hierarchies. Restrict project roles
using the Maintain Project Roles
task. |
How do you want to organize your project roles? | You can specify the categories for organizing the project roles on
the resource plan lines. Use the Maintain Project Role
Categories task to add or change your values. |
How do you want to approve new or modified resource plan
lines? | To enable manual approvals, configure the Project Resource Plan
Line business process.If you don't configure this business
process, Workday automatically approves both new and modified
resource plans. |
How do you want to approve new project workers? | To enable manual approvals, configure the Request Worker
business process.If you don't configure this business process,
Workday automatically approves new project workers. |
Do you want to differentiate between the confirmed and potential
workers assigned to a resource plan line? | You can configure the project booking status to specify the
commitment level of a worker on their assigned resource plan line. Use
the Maintain Project Booking Status task to
specify the values.Example: Hard Booked and Soft
Booked. |
Do you want to restrict project workers to selecting only their
assigned projects in their expense reports? | You can restrict the project worktags that workers can select when
they create or edit an expense report. To limit workers to selecting
only the worktags for their project assignments, configure the
Expenses Options section on the
Edit Tenant Setup - Financials
task. |
Recommendations
Configure the
Find Workers
button to open the Find
Available Workers for Project
report to streamline the staffing
process. This report enables managers to see an overview of worker qualifications
and their availability all at once.Create templates for your resource plans to reduce the time users spend on data
entry. The templates prefill the fields with information that is common to all your
projects.
Configure resource scheduling to view and manage resource assignments from 1 location
with the
Manage Worker Assignments
report. Create your resource plans at the project-hierarchy level when the projects within
the same hierarchy use the same resource plan. This configuration:
- Reduces the time spent on data entry.
- Maintains consistency.
- Avoids errors.
Restrict project roles to specific primary project hierarchies to streamline data
entry.
Requirements
Before you can create resource plans, you must first create project:
- Hierarchies.
- Roles.
Limitations
You can't add the same worker to more than 1 resource plan line when the worker
has:
- The same project role.
- Overlapping dates.
- Different standard cost rates.
You can't delete a resource plan line when:
- A task resource references the resource plan line.
- It has a pending worker assignment.
Tenant Setup
Access the
Projects
and Expenses
Options
sections on the Edit Tenant Setup -
Financials
task to configure the project-specific options.Depending on how you configure your resource plans in Workday, you can:
- Set the date range within which workers can record their hours on a project.
- Enable project and resource managers to use a specific report for staffing their projects. Managers launch this report from theFind Workersbutton.
- Restrict workers to select project worktags associated with their assigned resource plans.
- Enable resource scheduling to use theManage Worker Assignmentsreport.
Security
Domains | Considerations |
|---|---|
Business Process Administration in the System functional
area. | Users secured to this domain can edit the Project Resource Plan
Line and Request Worker business processes. |
Manage: Business Process Definitions in the System
functional area. | Users secured to this domain can manage the Project Resource
Plan Line and Request Worker business
processes. |
Set Up: Project in the Projects functional area. | Users secured to this domain can:
|
Set Up: Project Hierarchy in the Project Tracking functional
area. | Users secured to this domain can create, edit, and view resource
plans on the project hierarchy. |
Set Up: Project Tracking in the Project Tracking functional
area. | Users secured to this domain can:
|
Manage: Project Resources in the Project Tracking functional
area. | Users secured to this domain can:
|
Manage: Advanced Project Resource Management in the Projects
functional area. | Users secured to this domain can use the Manage Worker
Assignments report. |
Set Up: Advanced Project Resource Management in the Projects
functional area. | Users secured to this domain can:
|
To ensure proper access, review these team member roles and activities:
Domain Security Roles | Considerations |
|---|---|
Finance administrator | Configures tenant setup information. |
Project administrator |
|
Project manager Resource manager |
|
Business Processes
Business Processes | Considerations |
|---|---|
Project Resource Plan Line in the Project Tracking functional
area | Enables users to:
Has a security policy that enables you to open up approvals to
various security groups. You can also enable manual advancement to the
next step by a business process administrator. Contextual security
for the supervisory organization is only available for workers assigned
to a project, not workers pending approval. Because of this security,
when you configure a definition step with a supervisory organization
manager, you must also configure a Worker is
Assigned condition rule. |
Request Worker in the Projects functional area | Enables changes in worker assignments or associations. This business
process:
|
Reporting
Reports | Considerations |
|---|---|
Manage Worker Assignments
| Use to:
To enable this report, set up resource scheduling. |
Find Available Workers for Project
| Use this report to find both qualified and available workers for
their projects. You can configure Workday to launch this report from
the Find Workers button on the resource plan
line. |
Find Worker for Project
| Project and resource managers use this report to find qualified
workers for their projects. Workday automatically launches this
report, by default, from the Find Workers
button on the resource plan line. |
You can use these report data sources to create custom reports:
- Project Resource Plan Line Events - All Statuseson the Project Resource Plan Line Event business object.
- Project Resource Requirementson the Project Resource Requirement Parameter business object.
- Project Roleson the Project Role business object.
- Project Standard Cost Rate Sheeton the Project Standard Cost Rate Sheet business object.
- Resource Plan Detailson the Project Resource Plan Detail business object.
- Resource Plan Details Searchon the Project Resource Plan Detail business object.
Integrations
Web Service | Considerations |
|---|---|
Get Resource Plans
Submit Resource
Plan | Manages data on resource plans and resource plan lines for both
project hierarchies and projects. Submit initiates the
Project Resource Plan Line business process for approval
only for resource plans on projects, not project
hierarchies. |
Get Requirements for Resource Plan
Put Requirements for
Resource Plan | Manages data on resource requirements for resource plans. |
Connections and Touchpoints
Feature | Considerations |
|---|---|
Resource Forecasts | You must have a resource plan with assigned resources to create a
resource forecast. |
Project Budgets | You can create a project budget based on a resource plan. |
Time Entry Templates | You can enable workers to log time on any project or project task,
even if they don't have an assignment on a resource plan. Use the time
entry template to enable this feature. |
Expenses | You can restrict project workers to select only the project
worktags for their assigned resource plans when they create an expense
report. Use the financial tenant settings to enable this
feature. |