Set Up Pay Component Related Calculations
- Create an earning or deduction.
- Create a related calculation or identify an existing one to use.
- Security:Set Up: Payroll (Calculations - Payroll Specific)domain in the Core Payroll functional area.
You can configure Workday to automatically calculate related calculations as part of an earning or deduction. When you add a related calculation to an earning or deduction definition, Workday creates a pay component related calculation (PCRC).
Example: The
Hourly Pay
earning uses a calculation of Hours (unprorated)
* Rate
, where Hours (unprorated)
and Rate
are related calculations. When you assign the related calculations to the earning, Workday forms 2 new PCRCs:- Hourly Pay - Hours (unprorated)
- Hourly Pay - Rate
To display hours on the
Actuals
tab of a worker's pay result, add the General Ledger: Hours
pay component group to any Hours
related calculation.When the pay component uses
Position
as a calculation worktag, Workday resolves the pay component separately for each valid position. To include positions the worker no longer holds, Workday recommends using a pay accumulation as the related calculation. Note: While pay component groups always filter by worktag, you can configure pay accumulations not to filter by worktag.You can also use non-numeric related calculations in pay component calculations. You can choose from:
- Date type related calculations that return dates.
- Numeric, Boolean, and text type related calculations that return numeric values.
You can’t change the input value type of a related calculation once the related calculation has been used in a pay component.
For Payroll for the U.S., you can’t use non-numeric related calculations for FLSA earning amounts.
- Access theEdit EarningorEdit Deductiontask.
- In theRelated Calculationsgrid on theEffective Datedtab, add a row for each pay component related calculation. Complete theRelated Calculationsgrid:
Option Description Related CalculationSelect a related calculation to calculate as part of the pay component. Example: SelectHoursandRatefor anHours * Rateearning calculation.If you select a Workday-owned calculation, ensure that it meets your requirements for proration, retro processing, and other conditions.If you configure proration for the related calculation, either by days worked or calendar days, and link it to a pay component with proration exceptions, thePay Components Not Subject to Proration (Exception)field displays when you view the pay component related calculation. You can't configure this field directly, either inEdit EarningorEdit Deduction.(Optional) If you select a related calculation that you use to report hours, select theAggregatecheck box. Workday then combines hours from pay inputs into a consolidated result line, improving pay calculation performance and enhancing pay result readability.Default CalculationDisplays the default calculation defined on theCreate Related Calculationtask.When the default calculation isPayroll Input, select theInput Allowed?check box on theRelated Calculationsgrid.Override Calculation(Optional) Override the default calculation with a different calculation or amount. Example: You can selectTimesheet: Approved Hours for Earningto retrieve the value forHours (unprorated)from Workday Time Tracking.If you selectPayroll Input, also select theInput Allowed?check box on theRelated Calculationsgrid.If you are using non-numeric data in your related calculation (Boolean, date, or text), you must enter an override calculation for a related calculation that is the same data type as the input value type of the related calculation. Note: Override and default calculations for non-numeric related calculations don't display on payroll results, but are still used to calculate pay component amounts. - (Optional) Complete theLimit Detailssection of theRelated Calculationsgrid:
Option Description ValueSelect a calculation, balance, or other element that serves as a limit for the value of the PCRC.Based OnWhen left blank, Workday compares the value of the PCRC against the limit value.You can also compare an aggregated amount, including the current PCRC, against the limit value. Select a pay accumulation or select from the prompt.Include Current ValueApplies to limits based on pay accumulations. Select which PCRCs to process before the PCRC of the current row when evaluating a limit.On the row for:- The PCRC to take first, leave theInclude Current Valuefield blank.
- The PCRC to take second, select the first PCRC.
- The PCRCs to take third, select the first and second PCRCs.
Example: You can configure the order in which Workday evaluates a limit based on the sum of PCRCs A, B, and C. If you want Workday to resolve A first, then B, and finally C, then:- For the related calculation A, leave theInclude Current Valuefield blank.
- For the related calculation B, selectAfrom theInclude Current Valueprompt.
- For the related calculation C, selectAandBfrom theInclude Current Valueprompt.
- (Optional) If you want to limit how a related calculation resolves for a worktag, complete theLimit Filter Worktagssection of theRelated Calculationsgrid:
Option Description Default Filter WorktagsWhen you assign a worktag limit to a related calculation, you can apply the limit at a worktag value level for a worktag dimension.Example: You create a related calculation tracking the amount paid toward the original amount requested for a 401k loan. You also add 2 payroll inputs for the 401k loan deduction specifying loan numbers 1 and 2. When you assign the 401k Loan number custom worktag dimension as a default filter worktag, the amount paid toward the loans is tracked separately by loan number.ConditionConditional Filter WorktagsUse these fields to configure a set of worktags for the limit, different from the worktags you configured as default.These worktags override the default if the conditions you configure are true. - Complete theResultssection of theRelated Calculationsgrid:
Option Description Do Not Store / Do Not Store if ZeroSelect whether to store the value of the PCRC with each calculation. Select:- Do Not Storeto improve performance when the PCRC is only used in an intermediary calculation.
- Do Not Store if ZeroorNone of the aboveto store the PCRC calculated value for later use. You can then display the calculated value, report on it, or make it available to other calculations.
Workday doesn't process retro differences that you generate for the PCRC in the target period when:- You selectDo Not Store if Zero.
- The pay component amount is zero.
To process retro on the PCRC in the target period regardless of the pay component value, selectNone of the above.When you selectInput Allowed?, Workday stores payroll input for the PCRC regardless of your selection.Display Current / Current and BalancesSelect what to display in theRelated Valuessection of theView Payroll Resultsreport for a worker:For Payroll for Canada, France, and the U.S.:- Display Current: Displays only the PCRC amount.
- Current and Balances: Displays both the PCRC amount and balances (such as MTD and PTD) configured on theMaintain Pay Results - Balance Period Mappingtask.
- None of the above: Doesn't display theRelated Valuessection.
For Payroll for Australia and the UK:- Display Current: Displays only the PCRC amount.
- Current and Balances: Displays both amount and balances (such as PTD and YTD) configured on theMaintain Pay Results - Balance Period Mappingtask.
- None of the above: Doesn't display theRelated Valuessection.
- In theHours for Reportingsection of theRelated Calculationsgrid, consider:
Option Description ResultFor hours-related calculations only. Select to include the PCRC value in the pay result.Workday then makes the hours PCRC value available for reporting through theHours Worked on Resultreport field. This report field comes from thePayroll Resultsdata source on thePayroll Resultsbusiness object.Workday uses the latest effective-dated pay component definition to determine the configuration for reporting hours.Result LineFor hours-related calculations only. Select whether toAddorSubtractthe hours PCRC value from the aggregation of all PCRC values for the pay result line.Workday then:- Makes the hours PCRC value available for reporting through theResult Line Hoursreport field. This report field comes from thePayroll Result Linesdata source on thePayroll Result Linebusiness object.
- Sums all result line hours and makes the result available for reporting through theHours Paid on Resultreport field. This report field comes from thePayroll Resultsdata source on thePayroll Resultbusiness object.
Workday uses the latest effective-dated pay component definition to determine the configuration for reporting hours. - As you complete the other fields on theRelated Calculationsgrid, consider:
Option Description Override Related Calculation for Ongoing Multiple JurisdictionsFor Payroll for the U.S.:Applies when defining one of these pay components:- A taxable earning.
- An imputed earning.
- A pretax deduction.
Companies using ongoing multiple work jurisdictions can split the PCRC by percentages. Define the percentages for employees on theTax Allocationstab of theAdd Worker US Tax Elections.To use theDefault Calculationsetting from the related calculation, selectNone of the Aboveor select an option to override it.TheDo Not Applyoption is available for pay components and for individual PCRCs. Determine whether to split the entire pay component or the PCRC.Retro Adjustment TypeDisplays when you selectBring Forward Differenceon theCreate Related Calculationtask.Indicates whether theRun Retro Pay Calculationtask forwards the difference between the original value and the recalculated value to the current period. When clear, Workday uses the full amount of the recalculated pay component related calculation in the current period instead of the retro differences.Pay Component Related CalculationDisplays the PCRC that results from defining the related calculation for the pay component.
You can:
- Select pay component related calculations in pay component groups, pay accumulations, and pay balances.
- Display pay component related calculations on payroll result reports and employee payslips.
When you run a payroll calculation, Workday calculates the pay component related calculations.